Farm Construction Contracts Explained
Contracts for barns, bins, shops and fencing should define scope, price, schedule, change orders, payment, insurance, warranties and lien protections before a contractor breaks ground.
A farm construction contract covers work such as building a barn, machine shed, grain bin, shop, greenhouse, manure storage or fence line. It is the agreement that defines what will be built, for what price, by when and under what conditions. Because construction projects are large, involve many people and can last months, loose terms tend to cause expensive disputes.
The essentials are a clear scope with plans and specifications, a stated price method, a payment schedule tied to progress, a process for changes, insurance and licensing proof, lien protection, a warranty and a plan for delays and disputes. Contractor licensing, lien law, building codes and agricultural exemptions vary by state and locality, so confirm requirements with your county and an attorney.
Scope, plans and permits
Start with a written scope: dimensions, materials, site preparation, utilities, finish level, who supplies what and who handles permits. Attach plans and specifications, and say what is not included, such as excavation, electrical service, concrete or tree removal.
Many places exempt some farm buildings from certain building codes, but exemptions are specific and may not cover buildings used by the public or for events. Zoning, setbacks, floodplain, stormwater and environmental rules may apply. See understanding agricultural zoning laws and fuel and storage tank rules for related rules. Put in writing who obtains each permit.
Price types
| Price method | How it works | Watch for |
|---|---|---|
| Fixed price | One agreed total | Change orders and allowances |
| Cost plus | Actual costs plus a fee or percentage | Need for a cap or estimate and records |
| Time and materials | Hourly and material charges | Open-ended totals |
| Unit price | Price per unit, such as per square foot or yard | Quantity measurement |
Ask for allowances, such as for soil conditions or finishes, to be listed separately. Decide how rising material prices will be handled, and whether prices are held for a stated time.
Payments, retainage and liens
Tie payments to milestones or to inspected progress, not just dates. A small deposit with the balance paid in stages helps protect you from paying far ahead of work. Some contracts hold back a portion, called retainage, until completion and punch list items are done.
Many states allow contractors, subcontractors and suppliers to file a mechanic's lien on the property if they are not paid, even if you paid the general contractor. To reduce the risk, ask for lien waivers with each payment, a list of subcontractors and suppliers, and proof that they were paid. State lien notice and filing rules differ, so ask an attorney. See also legal guide to farm subcontracting.
Change orders and delays
Changes happen: soil conditions, new equipment dimensions, material shortages. The contract should require written change orders that state the price change, time change and signatures from both sides before work proceeds. Verbal changes are a leading source of disputes.
Address schedule realistically. Weather, supply chain problems and inspections can delay work, but you may also have seasonal needs, such as a barn before winter or a bin before harvest. Consider a clause about what delays are excusable and whether there are remedies for unexcused delay. Avoid unrealistic penalties that a court may not enforce, and ask an attorney about enforceability.
Insurance, licensing and safety
Ask for proof that the contractor holds required licenses and insurance, including general liability and workers compensation where applicable. Get certificates directly from the insurer or agent. Check your own policy too, since a building under construction may require builder's risk coverage; see farm insurance requirements and coverage.
A contractor's workers on your land can create injury and liability risks. See farm indemnification clauses explained and how to limit liability on your farm. The OSHA agriculture pages and NIOSH agriculture resources provide safety information.
Warranties and completion
Specify warranties on workmanship and materials, how long they last, how claims are made and who is responsible for manufacturer warranties on products like roofing or doors. Define substantial completion, a final inspection, a punch list and final payment conditions. Keep manuals, product information, as-built drawings and warranty documents. For more detail see farm warranty and guarantee rules.
A hypothetical example
A hypothetical 300-acre hog and grain farm contracts for a machine shed at a fixed price of 120,000 dollars. The contract requires a deposit of 10 percent, then three progress payments, and holds back 5 percent until final inspection. The deposit is 10 percent of 120,000, or 12,000 dollars, and retainage is 5 percent, or 6,000 dollars.
During construction the owner asks for a larger door at an extra 3,500 dollars, and both sign a change order. The adjusted contract price becomes 123,500 dollars. With each payment, the contractor supplies lien waivers from the concrete supplier and the steel erector. At the end, the final inspection finds one punch list item, and the retainage is released after it is fixed. Written steps made the work boring in the best sense.
Building projects teach patience, and the FARM.FM Today pages are a good break while waiting on concrete. A well-built barn is worth the wait, and the ranching content at FARM.FM shows what happens when the fence crew and the weather disagree.
Checklist before signing
- Confirm contractor license, insurance and references.
- Attach plans, specifications and a schedule.
- Choose price method and list allowances.
- Set payment milestones, retainage and lien waiver process.
- Require written change orders.
- Define warranty, completion and punch list.
- Add a dispute clause; see how to void a farm contract legally for exit options and how to enforce a farm contract.
When to call a professional
Consult an attorney before signing a large construction contract and when a lien notice, payment dispute or defect appears. Bring plans, bids, the proposed contract, proof of insurance and licenses, a list of subcontractors and your loan documents. Your lender may require draw schedules and inspections, and your insurance agent can add builder's risk coverage. An engineer or building inspector can check quality. Your county planning office handles permits, and the NRCS can help with conservation-related structures. A CPA can advise on depreciation and cost recovery; see IRS Publication 946.
Frequently asked questions
Do I need a written contract for a small building?
Yes, even for small projects. A written scope, price and schedule prevents most misunderstandings.
What is a change order?
It is a written agreement to change the scope, price or schedule. Do not let work proceed on a change without one.
Can a subcontractor put a lien on my farm?
In many states, unpaid subcontractors and suppliers can. Lien waivers and payment records help, and state rules differ.
Are farm buildings exempt from building codes?
Some are partly exempt, but rules vary and often depend on use. Ask your county before you design or build.